When a developer changes project management in the middle of a build, it is rarely a good sign. It usually means time has been lost, money has gone out without matching progress and the people funding the project have stopped trusting what they are told. This case study covers a residential tower in Jumeirah Village Circle where DNA was appointed as chief PMC to take over from another management company and bring the project back on track.
“The project was initially with another management company who left our project with many issues in construction and execution including leaving many suppliers with pending payments … Despite all the issues, DNA Project Management was able to revive the entire project and bring back the full feasibility. They have rectified all the issues including completing more of the project in 1 year than the previous management company had been able to accomplish in 3 years.”
Artistic Legend Real Estate Development
Letter of recommendation, 16 February 2023
By the time DNA was appointed, the project had been with another management company for several years. According to the client, that company left the project with many issues in construction and execution, including suppliers with pending payments. The investors behind the development were not resident in Dubai, which made the situation harder: they were relying on reports from a distance, they were anxious about whether the problems could be fixed at all, and they were unsure whether a new consultant could restore the project’s feasibility.
That combination is common in stalled developments. Progress has slowed, the supply chain has lost confidence, and the owner has lost visibility. Fixing it takes more than a new programme.
A takeover starts with establishing the facts: what has been built, what has been paid for, what is owed and to whom, where the approvals stand and what the design still needs. Only then can the remaining work be planned honestly and the budget re-forecast to completion. For a development, that also means re-testing the feasibility with the real cost and time, so the investors can see whether the scheme still works and what has to change.
The supply chain has to be brought back. Suppliers who have not been paid will not deliver, so legitimate liabilities have to be settled on a documented basis and clear payment terms agreed going forward. From that point, every payment is certified against work measured on site and every change is priced and approved before it is instructed.
We have set out this process in more detail in our guide to taking over a stalled construction project in Dubai.
For the client, the central question was whether the project could still deliver the return it was planned for. In the client’s words, DNA was able to revive the entire project and bring back the full feasibility. That outcome depends on controlling the remaining cost and time from the day of handover, because every month of delay and every uncontrolled cost erodes the appraisal. Our article on development feasibility for Dubai investors explains how cost and time feed into the numbers.
The clearest measure of the turnaround is the client’s own: DNA completed more of the project in one year than the previous management company had been able to accomplish in three. The client also stated that without DNA, the project would have been at risk and would have cost far more money than allocated.
Speed after a takeover does not come from pushing the contractor harder. It comes from removing the reasons work had slowed: unresolved design questions, unpaid suppliers, unclear instructions, slow decisions and approvals left without a plan. Once those are dealt with and a realistic baseline programme is in place, progress can be measured honestly every month, and slippage shows up early enough to act on.
For owners and investors based outside the UAE, reporting is the project. A short monthly report showing measured progress against the baseline, forecast final cost against budget, cash flow, open risks and decisions required, supported by photographs, gives them a position they can rely on without being on site. It also rebuilds the trust a stalled project loses. Our guide to construction project management services in Dubai covers what that reporting should contain.
Three points stand out. First, the warning signs of a stalling project appear long before the owner acts: unexplained slippage, suppliers chasing payments, payment applications approved without a clear link to progress. Acting earlier preserves more of the feasibility. Second, a takeover has to start with an honest audit rather than optimism. Third, a stalled project can be recovered: the right controls, a re-baselined programme and a supply chain that trusts the project again can change the pace of a development within months.
The client summed up the relationship plainly, saying it was looking forward to giving DNA more work and that any individual or company would be pleased to work with DNA and its team.
Many of the problems on a stalled project trace back to decisions made before construction, which is the work covered in our guide to development consultancy in Dubai.
DNA acts for developers, corporate and private clients as project management consultant, owner’s representative and development manager. Read more of what our clients say, see our services, or contact us for a confidential conversation about a project that has stalled.
Yes. On this residential tower in JVC, DNA was appointed as chief PMC to take over from a previous management company, revived the project and restored its feasibility.
It depends on the project, but here the client reported that DNA completed more of the project in one year than the previous management company had achieved in three.
An honest audit of the current position, a re-baselined programme and budget, a re-tested feasibility and a monthly report showing measured progress, cost to complete, cash flow and decisions required.