Projects in Dubai rarely stop in one dramatic moment. They slow down. Payments to suppliers fall behind, the programme slips month by month, reports become vague and the owner starts to hear about problems from the site rather than from the people managing it. By the time the owner decides to change project management, the project has usually lost both time and trust.
Taking over a project in that state is different from starting one. This guide sets out how a new project management consultant restarts a stalled construction project, and what an owner should expect in the first weeks.
Any one of these can be fixed. Several together usually mean the project is no longer being controlled.
Before anything can be restarted, the new team has to establish the facts. That means reviewing the contracts and their current status, every payment certified against work actually completed, outstanding supplier and subcontractor liabilities, the approvals position with each authority, the quality of work already built, and the true state of the design. Site measurement matters here. Paperwork describes what was claimed; the site shows what was built.
The result is a clear picture for the owner: what has been paid for, what exists, what is owed, what is missing and what has to be redone. It is rarely comfortable reading, but every later decision depends on it.
With the facts established, the project needs a new baseline. The remaining work is re-planned from the actual position, including outstanding approvals and long-lead items. The budget is re-forecast to completion, including any rectification and the cost of settling legitimate liabilities. Where the project is a development, the appraisal is re-run with the new cost and time, so the owner can see whether the scheme still makes sense and what has to change for it to work.
This is also the point to decide whether the existing contractor can complete the job under tighter control, or whether parts of the scope have to be re-tendered. Our article on the mistakes owners make when hiring a contractor in Dubai covers what to check if a new contractor is needed.
Owners often assume the contractor is the problem. Sometimes it is. But a contractor working without a clear programme, prompt decisions, fair certification and a single channel of instruction will struggle regardless of its ability. Replacing a contractor mid-project is expensive and slow, so it is worth establishing first whether the contractor or the management around it is the real cause. In many cases, tighter control of the existing contractor is the faster route to completion.
A stalled project often has a supply chain that has stopped trusting it. Suppliers who have not been paid will not deliver, and subcontractors will move their best people elsewhere. Part of the restart is settling what is actually owed, on a documented basis, and agreeing clear payment terms going forward. From then on, every payment is certified against work measured on site, and every variation is priced and approved before it is instructed.
Owners of stalled projects, especially investors who are not in Dubai, usually need one thing above all: reporting they can believe. That means a short monthly report showing progress against the new baseline, forecast final cost against budget, cash flow, open risks and the decisions the owner needs to make, backed by photographs and measured progress rather than descriptions. Our guide to construction project management services in Dubai sets out what that reporting should contain.
A new PMC cannot undo payments already made or work already built badly. What it can do is stop the losses from growing, give the owner an honest position, and put controls in place so the remaining budget is spent on progress. The earlier an owner acts on the warning signs, the more of the original feasibility can usually be recovered.
For a real example, read our case study on taking over a stalled residential tower in JVC, where more was completed in one year than in the previous three.
DNA has taken over projects from other management companies and brought them back on track; you can read what our clients say. If your project has stalled, see our services or contact us for a confidential conversation. Our guide to project management consultancy in Dubai explains how the appointment works.
Yes, subject to the terms of the existing appointment. The handover should include all contracts, correspondence, payment records, approvals and drawings, and the new consultant should audit the actual position before taking responsibility for the programme and budget.
The audit and a reset programme and budget usually take a few weeks, depending on the size of the project and the state of the records. Work on site can often continue during that period under tighter control.
Liabilities are checked against delivered work and contract terms. Legitimate amounts are settled on a documented basis so the supply chain can resume, and new payment terms are agreed going forward.